Design Construction Impacts
Right of way is proceeding early due to the large number of parcels affected by this project and the rising costs of real estate. The hydraulic report was nearly completed last year. However, new requirements and some changes to the design will necessitate a new hydraulic report. This report will be completed in 2008. Coordination is continuing with the utility companies, especially Puget Sound Energy, on relocation of the utilities affected by the project. Additional Right-of-Way may be required to accomodate storm water treatment within WSDOT Right-of-Way. Increased Preliminary Engineering, R/ight-of-Way, and estimated Construction costs have resulted in a decrease in the scope of work to address only the most critical accident areas within the project limits.
Local private development has had some impact on this project recently. It is anticipated that additional private development will also occur within the project limits between now and the scheduled advertisement date. Design changes will be required to accommodate these developments.
|