SR 160 - SR 16 to Long Lake Road - Complete October 2009

Quarterly Project Report Update for Quarter Ending June 2009

Project Title & Location
SR 160 - SR 16 to Long Lake Road

Project Description
This safety improvement project flattens slopes from SR 16 to Phillips Road vicinity and increases road shoulder widths to 4 feet (6 feet between Estonia and Brasch). A two-way left-turn lane will be added from Fred Meyer to Brasch and left turn lanes will be added at Phillips Road. The project also creates flat bottom ditches for storage of treatment for runoff.

Contractor/Consultant
The project was awarded to RG/Bowers Construction Joint Venture on March 2, 2009 .

Recent Progress
Construction was started 4/2/09

Utility relocation completed prior to June 1.  A change order covering costs of utility impacts to the contractor was executed.

Contractor has completed roadway widening for sewer installation.

Design Construction Impacts
Agreement was reached with a property owner to replace an approach onto SR 160 with an approach onto a county road.

A change order was executed to remove unsuitable material that was designed to be used on the project from the project and replace it with select barrow.

Utility relocation work is scheduled to be completed by June 1st 2009.  The completion of the utility relocation is taking longer than originally planned. The Project Office and contractor have worked together in scheduling the project work to minimize conflicts between the utilities' relocation, and the project work, to maintain the project schedule.

Environmental Impacts / Compliance
The project has minimal environmental impacts, no wetlands will be directly impacted.  All completed slopes and open slopes that are not being worked are covered with temporary erosion control blankets.  The other project BMP's are in place and in good working order.

Impacts to Traffic
Some lane restrictions are needed during the widening and slope-flattening stages.  Single-lane alternating traffic are occuring nightly during construction.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering  August 2, 1999 August 2, 1999
Environmental Documentation Complete November 07, 2008 December 30, 2008
Right of Way Certification November 25, 2008 January 22, 2009
Contract Advertisement January 5, 2009 January 26, 2009
Open to Traffic October 6, 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $ 1.33  12.0%
Right-of-Way $ 3.54  32.0%
Construction $ 6.20  56.0%
Funded Project Costs $11.07 100.0%

Nickel funds included in above costs

$ 7.65 70.0%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Brenden Clarke, Project Engineer, (360) 874-3000