Project Title & Location
SR 16 - Burley-Olalla Interchange
|
Project Description
Constructs a new grade-separated interchange on SR 16 at Burley-Olalla Road to improve safety at this high accident location.
|
|
Contractor/Consultant
Project not advertised or awarded.
|
|
Recent Progress
Hydraulic Report reviewed and returned with comments to Hydraulic Designer on January 18, 2008. Hydraulic comments are being addressed. Project Open House held in Olalla on January 29, 2008. Plans, Specifications, and Estimate package is in review. Amendment to Offsite Mitigation Plan received February 14, 1008.
|
|
Design Construction Impacts
Two fish barriers will be removed and remediated to new fish passable structures.
|
|
Environmental Impacts / Compliance
Two fish barriers are being remediated. Cultural resource study completed for project limits. All required permits have been applied for.
|
Impacts to Traffic
Four lanes of SR 16 will be provided throughout the duration of the project. Traffic speeds through the area will be reduced to 40 MPH. With the exception of Emergency Vehicles, access at Burley Olalla Road, to and from SR 16 is anticipated to be closed for the duration of the project.
|