Project Title & Location
SR 14/Lieser Rd Interchange - Add Ramp Signal
|
Project Description
The westbound off-ramp from SR 14 to Lieser Road experiences back-ups due to high traffic volume. By constructing a traffic signal at the intersection of the off-ramp with Lieser Road, the project will reduce congestion to improve traffic flow and reduce potential collisions.
|
|
Contractor/Consultant
OTAK for preliminary design
|
|
Recent Progress
The project was advertised on December 31, 2007 and was awarded on January 24, 2008.
|
|
Design Construction Impacts
The Construction Office is working with the Contractor to establish the construction schedule and associated traffic impacts.
|
|
Environmental Impacts / Compliance
Environmental documentation completed.
|
Impacts to Traffic
The Construction Office is working with the Contractor to establish the construction schedule and associated traffic impacts. Project Office anticipates miminal traffic impacts.
|