WSDOT and its contractor are building the project in two major stages to help keep traffic flowing throughout construction. Each stage will affect the way you travel SR 14, so it's important to stay informed.

Sign up to receive email updates, or visit WSDOT's Travel Alerts and Construction Update Web pages. You can also call 511 or 1-800-695-ROAD to get up-to-date traffic impacts anywhere in the state.


Stage 1

SR 14 Camas-Washougal Project - Stage 1
Download larger image (.pdf, 1.69KB)

Stage 1 built roundabouts and the frontage road on the south side of SR 14.



Stage 2

SR 14 Camas-Washougal Project - Stage 2
Download larger image (.pdf, 1.96KB)

Drivers are temporarily shifted to the new two-lane frontage road while SR 14 is being widened under Stage 2. 

This stage of construction is expected to be complete in fall 2012.