Project Title & Location
SR 14/Camas Washougal - Add Lanes and Build Interchange
|
Project Description
Widen SR 14 to four lanes from 6th Ave. to SR 500/Union Road to relieve congestion. Included in the project will be new bridges over the East and West Camas Sloughs and an interchange will be constructed at SR 500/Union Road. This project will reduce collisions by restricting turns at the 2nd Street and 6th Street intersections, and placing median barrier on SR 14.
|
|
Contractor/Consultant
Skillings-Connolly Inc. for environmental reporting and preliminary design.
|
|
Recent Progress
The design team is continuing work on the project's design and is preparing the environmental documentation with an anticipated completion in 2008.
|
|
Design Construction Impacts
The design team is in the preliminary phase of construction staging and traffic control design. They will work to minimize traffic impacts to SR 14 and city streets as much as possible.
|
|
Environmental Impacts / Compliance
Major work activities associated with environmental documentation are anticipated to be completed in 2008. The Biological Assessment with formal consultation has been submitted.
|
Impacts to Traffic
The design team is currently assessing these impacts. The team will minimize impacts as much as possible.
|