SR 124 - East Jct. US 12 - Reconstruction - Complete April 2004

Quarterly Project Report Update for Quarter Ending September 2003

Project Title & Location

SR 124 MP 6.65 Curve Realignment –


Pasco Vicinity

Project Description
This project will reduce the number and severity of accidents by realigning the curve and widening the lane and shoulder widths.

Contractor/Consultant
(Project not yet advertised or awarded)

Recent Progress

The contract plans have been submitted to the Regional Office for review.  Right of Way plans and funding have been approved.  Real Estate Services are currently in the acquisition phase.

Design Construction Impacts
Currently there are no impacts that would affect the delivery date.

Environmental Impacts / Compliance
All environmental documents complete; no permits required.

Impacts to Traffic
Daily one-lane closures will be required with brief delays anticipated.

Project Milestones Scheduled Attained Milestone Outlook
Project Start Apr 01 Apr 01 Completed on schedule.
Environmental Document Aug 02 Completed on schedule.
Contract Advertised Dec 03 No impacts anticipated at this time
Contract Awarded Jan 04 No impacts anticipated at this time
Open to Traffic May 04 No impacts anticipated at this time
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.08 21.7 %
Right-of-Way $0.03 9.3 %
Construction $0.24 69.0 %
Funded Project Costs $0.35 100 %

Nickel funds included in above costs

$0.32 92.8 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Troy Suing, WSDOT Project Design Engineer @ (509) 577-1703 or E-mail: suingt@wsdot.wa.gov