SR 124 - East Jct. US 12 - Reconstruction - Complete April 2004

Quarterly Project Report Update for Quarter Ending March 2004

Project Title & Location

SR 124 MP 6.65 Curve Realignment –


Pasco Vicinity

Project Description
This project will reduce the number and severity of accidents by realigning the curve and widening the lane and shoulder widths.

Contractor/Consultant
Transtate Paving Co.

Recent Progress

Construction began on this project with the removal of existing asphalt roadway on March 16, 2004.  Sub grade construction near completion on March 23.  The paving is scheduled to be completed by March 31.  There are twenty working days for this project which will be up on April 12, 2004.  This project has been nominated for a 2004 Project Highlights Report.

Design Construction Impacts
Currently there are no impacts anticipated that would affect the delivery date.

Environmental Impacts / Compliance
All environmental documents complete; no permits required.

Impacts to Traffic
Daily one-lane closures with brief delays.  Both lanes will travel on unpaved section of roadway for several weeks.

Project Milestones Scheduled Attained Milestone Outlook
Project Start Apr 01 Apr 01 Completed on schedule.
Environmental Document Aug 02 Aug 02 Completed on schedule.
Contract Advertised Dec 03 Dec 03 Completed on schedule.
Contract Awarded Jan 04 Jan 04

Completed on schedule

Open to Traffic May 04 No impacts anticipated at this time
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.08 21.7 %
Right-of-Way $0.03 9.3 %
Construction $0.24 69.0 %
Funded Project Costs $0.35 100 %

Nickel funds included in above costs

$0.32 92.8 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects