Project Title & Location
SR 124 MP 6.65 Curve Realignment – Pasco Vicinity
|
Project Description
This project will reduce the number and severity of accidents by realigning the curve and widening the lane and shoulder widths.
|
|
Contractor/Consultant
Transtate Paving Co.
|
|
Recent Progress
Construction began on this project with the removal of existing asphalt roadway on March 16, 2004. Sub grade construction near completion on March 23. The paving is scheduled to be completed by March 31. There are twenty working days for this project which will be up on April 12, 2004. This project has been nominated for a 2004 Project Highlights Report.
|
|
Design Construction Impacts
Currently there are no impacts anticipated that would affect the delivery date.
|
|
Environmental Impacts / Compliance
All environmental documents complete; no permits required.
|
Impacts to Traffic
Daily one-lane closures with brief delays. Both lanes will travel on unpaved section of roadway for several weeks.
|