SR 124 - East Jct. US 12 - Reconstruction - Complete April 2004

Quarterly Project Report Update for Quarter Ending December 2003

Project Title & Location

SR 124 MP 6.65 Curve Realignment –


Pasco Vicinity

Project Description
This project will reduce the number and severity of accidents by realigning the curve and widening the lane and shoulder widths.

Contractor/Consultant
Project advertised for construction 12/8/03

Recent Progress
This project was advertised for Contractor bids on December 8, 2003.  Bid opening is scheduled for January 14, 2004. 

Design Construction Impacts
Currently there are no impacts anticipated that would affect the delivery date.

Environmental Impacts / Compliance
All environmental documents complete; no permits required.

Impacts to Traffic
Daily one-lane closures will be required with brief delays anticipated.

Project Milestones Scheduled Attained Milestone Outlook
Project Start Apr 01 Apr 01 Completed on schedule.
Environmental Document Aug 02 Aug 02 Completed on schedule.
Contract Advertised Dec 03 Dec 03 Completed on schedule.
Contract Awarded Jan 04 No impacts anticipated at this time
Open to Traffic May 04 No impacts anticipated at this time
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.08 21.7 %
Right-of-Way $0.03 9.3 %
Construction $0.24 69.0 %
Funded Project Costs $0.35 100 %

Nickel funds included in above costs

$0.32 92.8 %

2005 Transportation Partnership Account