Project Info

SR 121 - Blooms Ditch - Remove Fish Barriers - Complete September 2016

Overview
This project removed three culverts under State Route 121 and installed two large box culverts that are 26-feet wide and 16-feet wide respectively to improve fish passage in Blooms Ditch.

 

How you benefit

Protects environment
Replaces outdated culverts that are a barrier for fish with culverts that are built wider than the existing stream channel. They are also sloped like a natural stream. The wider culverts are intended to simulate what is found in a natural stream bed.

 

Funding

Financial Data for PIN 312103A
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $2,674
CWA $0
Total $2,674

 

Contact us
Tumwater Project Engineer Office
360-570-6750

WSDOT Olympic Region Communications
360-357-2789

Project vicinity map
View larger map

This detour is no longer needed after crews completed this work.