Prefabrication: Kiewit-General (K-G) carpenters create pontoon forms even before work starts in the graving dock. Prefabricating the forms and other pieces ahead of pontoon construction enabled crews to complete work inside the graving dock more efficiently. January 2006.
|
 |
Preparations: Crews prepare the graving dock for moving forms, rebar and other supplies from storage areas to inside the 150-foot wide by 465-foot long graving dock. March 2006
|
 |
Forms Installed: Carpenters set up and install the first pontoon wall forms for pontoon PA. March 2006
|