| East-half Approach Span Rollover: The new approach span was rolled into place at 12 a.m. Tuesday, August 23.
|
 |
| East-half Approach Span Rollover: The permanent bearing pads for Piers 6-10 were all installed by 11 a.m. Tuesday, August 23. |
 |
Pave and stripe roadway: Crews pave the section connecting the roadway to the new approach span. 7 p.m. Tuesday, August 23. The bridge opened to traffic at 8:42 p.m. Tuesday, August 23.
|