| East-half Approach Span Rollover: Crews saw cut the existing approach span away from the transition span. 2 a.m. Monday, August 22
|
 |
| East-half Approach Span Rollover: The existing west approach span rolling southward to the temporary falsework. 6 a.m. This roll was completed at 4 p.m. Monday, August 22. |
 |
East-half Approach Span Rollover: Work began on approach roadway replacement. 7 a.m. Monday, August 22
|