Take a closer look at how the Hood Canal Bridge Project progressed by visiting the construction cameras. The cameras provide a bird's-eye view of the work and show how WSDOT prepared for the bridge's closure and east-half replacement in May-June 2009.
Pontoon outfitting: Todd Pacific Shipyards, Seattle
WSDOT and Kiewit-General crews completed working on all pontoons at Todd Pacific Shipyards (TPS). The sections were installed on the new bridge, which reopened June 3, 2009.
See how work on the draw span pontoons progressed at TPS...
See how outfitting work progressed on the new roadway pontoon... Pontoon UVWX was completed and floated out of TPS on March 30, 2009 and arrived in Port Gamble Bay on March 31, 2009.
Cycle four pontoons construction: Concrete Technology Corporation, Tacoma
With the fourth cycle of pontoon construction complete, crews from WSDOT and Kiewit-General have completed work at Concrete Technology Corporation.
See how the work progressed...