Rail - Tacoma RMDRR Morton Line Repairs – Phase 2 - Complete June 2005

Quarterly Project Report Update for Quarter Ending December 2003

Project Title & Location
Tacoma R.M.D. RR Morton Line Repairs - Phase 2– Pierce & Lewis Co.

Project Description
Constructs Phase 2 of Tacoma Rail Mountain Division’s Morton line upgrade to restore rail service after 1996 floods, maintaining more than 200 jobs and potential to divert 16,000 heavy truck trips per year from state highways.

Contractor/Consultant
City of Tacoma

Recent Progress
Construction began in July 2003, under a small contract for immediately needed upgrades, with that portion completed in mid-December.  Construction will continue under a second agreement scheduled to begin in early 2004 to complete the upgrades and increase traffic on the rail line.  Full completion is anticipated before the end of the biennium.

Design Construction Impacts
No construction issues were encountered during the now-completed first stage of construction and none are anticipated during the final stage.

Environmental Impacts / Compliance
Contractually the railroad is responsible for all environmental impacts and compliances.  It is anticipated there may be some issues due to bridge repairs and the proximity of general rehabilitation to wetlands.

Impacts to Traffic
Track work will be done around scheduled train operations.

Project Milestones Scheduled Attained Milestone Outlook
Begin Construction Jan 04 Jul 03 Construction began 6 months ahead of schedule.
Construction Complete Jun 05 Construction will be completed on time and within the allotted budget.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.0 0.0%
Right-of-Way $0.0 0.0%
Construction $3.18 100%
Funded Project Costs $3.18 100%

Nickel funds included in above costs

$3.18 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Kevin Jeffers, Rail Passenger Engineer @ 360-705-7982 or E-mail: rail@wsdot.wa.gov