Rail - Stanwood - New Station

Quarterly Project Report Update for Quarter Ending March 2009

Project Title & Location
Stanwood - New Station

Project Description
The $5.0 million project would establish the station facilities needed for a new Amtrak Cascades stop in Stanwood.

Contractor/Consultant
HDR Inc., Amtrak, and Interwest Construction

Recent Progress
This project will design and construct a new passenger platform and other facilities at Stanwood to be served by Amtrak Cascades trains.

Amtrak awarded the construction contract to Interwest Construction of Burlington in mid-March.  WSDOT, Amtrak, and the contractor are working out final construction-related details with the city of Stanwood.  Construction is scheduled to begin in mid-April, with completion scheduled for September 2009.

Design Construction Impacts
The station will be located between 271st Street and a power substation in downtown Stanwood.  It is unlikely that construction will have an adverse impact on the community, as the site is a vacant lot.  However, construction of the station and adjacent roadway improvements could have a temporary impact on rail operations in the area.

Environmental Impacts / Compliance
WSDOT has prepared a State Environmental Policy Act (SEPA) checklist for this project.  A Cultural Resources Report and Biological Assessment have also been prepared.  Please visit the WSDOT Environmental Services Web site for more information.

Impacts to Traffic
Only minor impacts to local roadway traffic is anticipated during construction.

Project Milestones Scheduled Attained Milestone Outlook
Project Report Complete Mar 2006 Mar 2006
Begin Preliminary Engineering Apr 2006 Apr 2006
Complete Environmental Documentation Apr 2007 Jan 2008
Construction Begins Oct 2008 Construction will begin in April 2009.
Construction Complete Jun 2009 Construction is scheduled to be completed in September 2009.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.376 7.5%
Right-of-Way $0.2 4.0%
Construction $4.424 88.5%
Funded Project Costs $5.0 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

$5.0 100%

  For more information, go to www.wsdot.wa.gov/projects

Kirk Fredrickson, Project Manager at 360.705.7939 or E-mail: fredrik@wsdot.wa.gov