Rail - Stanwood - New Station

Quarterly Project Report Update for Quarter Ending June 2008

Project Title & Location
Stanwood - New Station

Project Description
The $5.0 million project would establish the station facilities needed for a new Amtrak Cascades stop in Stanwood.

Contractor/Consultant
BNSF Railway, Fort Worth, Texas

Recent Progress
 

This project will design and construct a new passenger platform and other facilities at Stanwood to be served by Amtrak Cascades trains.

It was previously reported that this project was delayed by a lack of funding for a new siding track near the station site and propsed federal platform design requirements opposed by the BNSF Railway.  Both of these issues have been resolved.  However, due to uncertainty of the closure of Logen Road as part of the Stanwood - Siding Upgrade project, BNSF cannot commit to allowing construction of the station platform at this time.  As discussions regarding the closure of Logen Road continue, WSDOT and Amtrak are proceeding with utility relocations at the station site and the execution of a construction management agreement.

Design Construction Impacts
The station will be located between 271st Street and a power substation in downtown Stanwood.  It is unlikely that construction will have an adverse impact on the community, as the site is a vacant lot.  However, construction of a platform could have a temporary impact on rail operations in the area.

Environmental Impacts / Compliance
WSDOT has prepared a State Environmental Policy Act (SEPA) checklist for this project.  A Cultural Resources Report and Biological Assessment have also been prepared.  Please visit the WSDOT Environmental Services Web site for more information.

Impacts to Traffic
Only minor impacts to local roadway traffic is anticipated during construction.

Project Milestones Scheduled Attained Milestone Outlook
Project Report Complete Mar 2006 Mar 2006
Begin Preliminary Engineering Apr 2006 Apr 2006
Complete Environmental Documentation Apr 2007 Jan 2008
Construction Begins Oct 2008 Construction will begin in January 2009, pending BNSF approval.
Construction Complete Jun 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.376 7.5%
Right-of-Way $0.2 4.0%
Construction $4.424 88.5%
Funded Project Costs $5.0 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Kirk Fredrickson, Project Manager at 360-705-7939 or E-mail: fredrik@wsdot.wa.gov