|
Recent Progress
Watco and WSDOT provided verbal commitments to Spokane County to allow the connection needed with the PCC CW rail line, and have promised to provide written authority. The project depends on approval by the Surface Transportation Board, which could require an extensive environmental review process. Spokane County submitted its plans to approach the STB to an attorney specializing in STB law, and expects to resolve all STB issues by the end of August 2006.
The 30% plans were completed in May 2006 under a federal grant. New estimates show that the project will cost $5.6 million; however, this included a 20% contingency on many remaining unknowns. WSDOT and the County are reviewing the plans for cost savings and other changes. The County is also considering whether it can cover costs above the amount provided by this grant.
|