Rail - Produce Railcar Pool

Quarterly Project Report Update for Quarter Ending June 2008

Project Title & Location
Produce Railcar Pool, Eastern Washington

Project Description
Provide Washington's agricultural community with pool of rebuilt refrigerated railcars to access for perishable shipping.

Contractor/Consultant
Rail Logistics, LC

Recent Progress
Since the program began in August 2006, over 355 refrigerated railcar shipments have been made.  Seventy five percent of shipments in the program have been frozen fruit and the remainder have been fresh or frozen vegetables.

Design Construction Impacts
None.

Environmental Impacts / Compliance
None.

Impacts to Traffic
None.

Project Milestones Scheduled Attained Milestone Outlook
Contract Complete Jun 2006 Aug 2006  
Service Begins Jul 2006 Aug 2006  
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering
Right-of-Way
Construction
Funded Project Costs $1.974 100%

Nickel funds included in above costs

2005 Transportation Partnership Account