|
Recent Progress
This project will construct main line tracks to allow eastbound and northbound freight trains to by-pass the rail yard in Vancouver. A rail siding for stopping freight trains clear of the north-south main line and a new vehicle overpass would also be constructed. This will free up capacity on the north-south main line, improving on-time performance of the Amtrak Cascades trains, and is a step toward the addition of a fifth Seattle-Portland round trip.
In July 2006, WSDOT requested to advance $4.935 million in 2003 Transportation Package funds and another $2 million in dedicated federal funds for this $109,950,000 project from the 2007-2009 biennium. This would allow completion of Pre-construction Engineering and continue Right-of-Way purchases in the current biennium. This action was approved by the Office of Financial Management in September 2006.
The design of the W 39th Street Bridge has been completed to 30 percent and revised estimate and schedule have been produced by WSDOT and its consultant. The bridge construction is now scheduled to go to advertisement in March 2008, about six months later than the November 2007 date previously set. This is due to the longer than anticipated time required for purchasing property for the project. In addition to the delay of starting the bridge construction, the most recent estimates indicated the costs for the required property, and constructing the bridge and related work, will be $7 million more than the $13 million indicated in the previous estimate. This is due primarily to the inflation in property, and the need for a wider embankment and structure to accommodate a second sidewalk, as well as higher than anticipated costs for storm water treatment and other utility relocations.
BNSF Railway has completed their operations modeling work for the rail portion of the project, and should restart engineering in October 2006. It remains possible to begin construction in late 2007 of some portions of the track and signal work, and relocation of some rail facilities in advance of the W 39th Bridge construction.
|