Rail - Tenino - High Speed Crossovers

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
Tenino - High Speed Crossovers, Tenino

Project Description
Constructs universal high speed (50 mph) crossovers near Tenino. The is part of the capacity improvements to support the 5th Amtrak Cascades round trip.

Contractor/Consultant
BNSF Railway, Forth Worth, TX

Recent Progress
A task order to cover pre-construction engineering and environmental activities associated with the project has been prepared and sent to BNSF Railway for their review and subsequent approval.


Design Construction Impacts
None.

Environmental Impacts / Compliance
Pre-construction engineering will address any environmental impacts.

Impacts to Traffic
There may be some brief work windows that may affect rail operations for both freight and passenger trains as new track and switches are connected to the existing track.  Amtrak Cascades passengers may occasionally be moved by motor coach to allow for these work windows. 

Project Milestones Scheduled Attained Milestone Outlook
Project Definition Complete Sep 2007 Sep 2007
Pre-construction Engineering Begins Jan 2008
Engineering Complete Jun 2008
Construction Begins Jan 2009
Construction Complete Jun 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.4 10.3%
Right-of-Way
Construction $3.475 89.7%
Funded Project Costs $3.875 100%

Nickel funds included in above costs

$3.875 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Carolyn Simmonds, Project Manager, at 360.705.7992 or E-mail at simmonc@wsdot.wa.gov