Rail - Stanwood Siding Upgrades

Quarterly Project Report Update for Quarter Ending June 2008

Project Title & Location

Stanwood Siding, Snohomish County

Project Description
Currently, passenger and freight trains can be delayed up to 70 minutes due to the poor condition of siding at Stanwood. This project will upgrade the siding track to provide faster and more reliable passenger service.

Contractor/Consultant
BNSF Railway Co., Fort Worth, TX

Recent Progress
This project will upgrade the siding track to provide faster and more reliable passenger service.  Construction work started in May 2008 with laying of new track and concrete ties for the main line track and siding near the future Amtrak Station.

The siding upgrade project has been expanded by the Legislature.  This will extend the siding to allow future passenger service to stop at the planned Stanwood Amtrak Station.  Siding extension project planning started in March 2008, addressing environmental permitting, road closures, and preliminary engineering.  It is projected that environmental permitting will take up to 180 days to complete.  BNSF is coordinating the process to close one private and one public road crossing.

Design Construction Impacts
The project scope expansion has delayed the completion of engineering.  The upgrade of the siding is coordinated with the proposed Stanwood Station and proposed siding extension.

Environmental Impacts / Compliance
The first phase of the project, the upgrade of the existing track, requires only documentation for compliance with both the National and State Environmental Protection Acts.  The second phase of this project may require extensive evaluation due to mitigation of wetlands.

Impacts to Traffic
There may be some brief work windows that may affect rail operation for both freight and passenger trains as old signals are replaced with new signals.  Amtrak Cascades passengers may experience short delays on trains traveling between Vancouver or Bellingham and Seattle.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering Jul 2006 Sep 2006 
Environmental Documentation Complete Jun 2007 May 2008 Siding upgrade required very little environmental documentation.  Siding extension will need mitigation of wetlands and road closures; this is projected to take up to 180 days.
Construction Begins  Jul 2008 May 2008
Construction Completed Jun 2009 May be delayed into 2010, because of environmental impacts.
   
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.25 2%
Right-of-Way
Construction $15.70 98%
Funded Project Costs $15.95 100%

Nickel funds included in above costs

$15.95 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Lynnette Gregory, Project Manager at 360-705-7903 or E-mail: gregorl@wsdot.wa.gov