Rail - Tacoma - Bypass of Point Defiance

Quarterly Project Report Update for Quarter Ending March 2006

Project Title & Location
Pt Defiance Bypass-Phase 1, Pierce Co., WA

Project Description
Constructs and upgrades part of the mainline tracks along a 20-mile corridor for passenger service. Results in 6-minute reduction in Seattle-Portland schedule.

Contractor/Consultant
Sound Transit, Seattle, & Tacoma Rail, Tacoma

Recent Progress

WSDOT has developed a phased plan for the project using existing state funds.  Phase 1 will construct improvements that will allow Amtrak Cascades trains to use the bypass route without being delayed by freight or Sounder commuter trains.  This will also reduce travel times between Seattle/Tacoma and Portland by six minutes. 

 

Sound Transit and WSDOT have discussed cost sharing and joint construction of this project.  However, the two agencies have different timelines for construction.  Sound Transit intends to complete their project by the end of 2007.  State funds for construction on the shared rail line do not become available until mid-2007 ($3.5 million), mid-2009 ($16.9 million), and mid-2011 ($37.4 million).  This will prevent the two agencies from constructing the projects simultaneously and potentially reducing costs for both Sound Transit and WSDOT.

 

Recently, Sound Transit and WSDOT began exploring the feasibility of constructing a new grade separation in downtown Tacoma that would support more efficient passenger train operations and ensure public safety.  WSDOT has met with Sound Transit to discuss preliminary cost estimates for the structure and the acquisition of additional land.  However, neither agency has funds for a Pacific Avenue grade separation.  If additional funding can be secured for this grade separation project, it would solve operational challenges associated with the current alignment and eliminate two at grade crossings on Pacific Avenue and South Tacoma Way.

 

The Washington State Legislature has moved project funds from the 2009-2011 and 2011-2013 biennia to 2007-2009 so that WSDOT and Sound Transit could coordinate the design and construct the rail line at the same time and maximize the value of public funds. 

Design Construction Impacts
The construction impacts have not been determined.

Environmental Impacts / Compliance
The environmental impacts have not been determined.

Impacts to Traffic
Impacts to rail and roadway traffic have not been determined.

Project Milestones Scheduled Attained Milestone Outlook
Engineering Complete Jun 2009
Right-of-Way Purchased Jun 2011
Construction Begins Jul 2010
Construction Complete Jun 2013
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $5.9 10%
Right-of-Way $0.2 0%
Construction $48.0 89%
Funded Project Costs $53.5 100%

Nickel funds included in above costs

$13.7

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Kevin Jeffers, Rail Engineering Manager at 360-705-7982 or E-mail: jefferk@wsdot.wa.gov