Rail - Mt. Vernon Siding Upgrade

Quarterly Project Report Update for Quarter Ending March 2009

Project Title & Location
Mt. Vernon Siding Upgrade – Mt. Vernon

Project Description
Completes contractual commitments with the host railroad to upgrade the existing rail siding for on-time reliability. Guarantees the continued operation of the second train on this route, currently operating between Seattle and Bellingham.

Contractor/Consultant
BNSF Railway, Fort Worth, Texas

Recent Progress
This project requires the closure of Hickox Road at-grade crossing.  BNSF petitioned the Washington Utilities and Transportation Commission (WUTC) in April 2008 to close the crossing.  The WUTC held subsequent hearings and issued an order to close the crossing with some conditions.  The WUTC responded to the reconsideration request by an adjacent land owner in mid-January 2009.  The WUTC did not change its Final Order except to add cul-de-sacs on either side of the at-grade crossing, increasing the cost of the project up to $75,000.

WSDOT proposed that the project be moved into the 2011-2013 biennium as BNSF seeks additional funding.

In January 2009 the State was notified that the lawsuit against the State Rail and Marine Office was dismissed.

Design Construction Impacts
Design of Phase one began April 2004.

Environmental Impacts / Compliance
The first phase of the project, the upgrade of the existing track, required only documentation for compliance with both the National and State Environmental Policy Acts.  The second phase of the project, the siding extension, required a biological assessment to determine its effects on endangered species.   In February 2006 a wetland was discovered; a wetland fill permit has been processed.

Impacts to Traffic
There may be some brief work windows that may affect rail operation for both freight and passenger trains as old signals are replaced with new signals.  Amtrak Cascades passengers may experience short delays on trains traveling between Vancouver or Bellingham and Seattle.  The Hickox Road at-grade crossing may need to be closed to allow the siding extension to be used.

Project Milestones Scheduled Attained Milestone Outlook
Phase I Operationally Complete May 2005 May 2005 Phase I upgrades the existing siding track and signals.
Environmental Documentation Complete Jun 2007 Jun 2007 Engineering was completed June 2007.
Phase II Construction Begins Apr 2008 Was not met due to WUTC action & lack of BNSF funding.  Project placed on hold waiting BNSF Funding.
Phase II Operationally  Complete Apr 2009 Delayed.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.6 42%
Right-of-Way
Construction $2.2 58%
Funded Project Costs $3.8 100%

Nickel funds included in above costs

$3.8 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Andrew Wood, Project Manager at 360.705.7938 or E-mail: woods@wsdot.wa.gov