Rail - Mt. Vernon Siding Upgrade

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
Mt. Vernon Siding Upgrade – Mt. Vernon

Project Description
Completes contractual commitments with the host railroad to upgrade the existing rail siding for on-time reliability. Guarantees the continued operation of the second train on this route, currently operating between Seattle and Bellingham.

Contractor/Consultant
BNSF Railway, Fort Worth, Texas

Recent Progress
The Washington Utilities and Transportation Commission (WUTC) hearings regarding the proposed closure of the Hickox Road at-grade crossing were finished the end of February.  The WUTC's final decision is anticipated to be made by April 2008.

In October 2007 the city of Mount Vernon filed a lawsuit against the State Rail and Marine Office for filing improper notice in preparation for the closure of the Hickox Road at-grade crossing.  The lawsuit is still pending.  Neither the city nor WSDOT has taken any further action pending the decision of the WUTC in closing the crossing.

Construction start is planned for April 2008, barring adverse determination of WUTC on the proposed crossing closure.

Design Construction Impacts
Design of Phase one began April 2004.

Environmental Impacts / Compliance
The first phase of the project, the upgrade of the existing track, required only documentation for compliance with both the National and State Environmental Policy Acts.  The second phase of the project, the siding extension, will require a biological assessment for its effects on endangered species.   In February 2006 a wetland was discovered; a wetland fill permit has been processed.

Impacts to Traffic
There may be some brief work windows that may affect rail operation for both freight and passenger trains as old signals are replaced with new signals.  Amtrak Cascades passengers may experience short delays on trains traveling between Vancouver or Bellingham and Seattle.  The Hickox Road at-grade crossing may need to be closed to allow the siding extension to be used .

Project Milestones Scheduled Attained Milestone Outlook
Phase I Operationally Complete May 2005 May 2005 Phase I upgrades the existing siding track and signals.
Environmental Documentation Complete Jun 2007 Jun 2007 Engineering was completed June 2007.
Phase II Construction Begins Apr 2008 Dependent on WUTC hearing for Hickox Road closure; now anticipated to begin in April 2008.
Phase II Operationally  Complete Apr 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.1 3.3%
Right-of-Way
Construction $3.7 96.7%
Funded Project Costs $3.8 100%

Nickel funds included in above costs

$3.8 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Lynnette Gregory, Project Manager at 360-705-7903 or E-mail: gregorl@wsdot.wa.gov