Project Title & Location
Everett - Delta Jct. Curve Realignments and Delta Yard Storage Tracks
|
Project Description
Realigns curves to improve speeds for passenger trains up to 50 mph, a 15-20 mph increase. Results in a 2-minute reduction in Seattle-Vancouver, BC schedule. Also guarantees the continued operation of the second train on this route.
|
|
Contractor/Consultant
BNSF Railway, Fort Worth, Texas
|
|
Recent Progress
This project will realign curves to improve speeds for passenger trains and guarantees the continued operation of the second train on the Seattle-Vancouver, BC route.
The project will require BNSF to fill wetlands on their property, which then must be mitigated. As previously reported, BNSF is awaiting wetland permitting, which has delayed the anticipated start of construction until at least October 2007.
WSDOT had anticipated some delay in BNSF getting the required permits, so $8 million had previously been moved from the 2005-2007 biennium to the 2007-2009 biennium through the Section 603 process. As a result of the latest information, WSDOT will under spend on the project by about $5 million in the 2005-2007 biennium. WSDOT will seek to reappropriate the unspent 2005-2007 funds into the 2007-2009 funds.
|
|
Design Construction Impacts
Data collection and the early stages of design began in August 2003. The city of Everett has been willing to be involved in the design to ensure other rail improvements that they are planning are accommodated.
|
|
Environmental Impacts / Compliance
The project will involve the filling of wetlands, an assessment of biological impacts, and will require a Shoreline Permit from the city of Everett.
|
Impacts to Traffic
There may be some brief work windows that may affect rail operations for both freight and passenger trains as new track is connected to the current track. Amtrak Cascades passengers may occasionally be moved by motor coach to allow for these work windows.
|