Recent Progress
This project will reduce travels times through the area and provide storage tracks to keep freight switching work off the main line. This will result in improved on-time reliability for trains traveling north of Seattle. The 2003 Funding Package provided $1 million in 2003-2005 for Pre-construction Engineering on this project and $13 million in 2005-2007 biennium for construction.
Pre-construction engineering began in August 2003, but issues with scope design and wetlands have resulted in the engineering not being completed by July 2005, as anticipated. The delays in engineering and environmental permitting will cause the start of construction to be delayed until the winter of 2007.
To account for the delay, WSDOT has proposed to reprogram $8 million in 2003 “Nickel” funds from the 2005-2007 biennium into the 2007-2009 biennium. The department has also proposed to advance other Rail projects to make use the of the $8 million expenditure authority in the 2005-2007 biennium. These actions require approval by the Office of Financial Management.
As part of the Pre-construction Engineering, BNSF consultants have been geotechnical drilling in the project area.
|