Rail - Palouse River and Coulee City RR - Acquisition and Rehabilitation

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location
Palouse River & Coulee City RR Acquisition -- Grant, Lincoln, Spokane, Whitman, & Adams Counties

Project Description
Purchase the 296-mile Palouse River and Coulee City RR to preserve the transportation corridors for long-term availability. Select operators for each Branch and make emergency repairs to provide an immediate opportunity for economically viable freight transportation operations.

Contractor/Consultant
Watco Transportation Services Inc. d/b/a/ Palouse River and Coulee City Railroad (PCC), Rosalia, WA

Recent Progress
PCC, WSDOT, and lessees along the rail lines began establishing the boundaries for each lease.  The set boundaries will be used to prepare a deed from PCC to WSDOT, and to begin a real property management program.

WSDOT staff continued to identify areas needing rehabilitation along each branch of the purchased railroad.  The information will provide a basis for selecting the most urgent and beneficial projects for construction in the spring and summer of 2008 using funds appropriated for that purpose.

WSDOT began working with local governments to explore formation of rail districts or other intergovernmental entities.  When such agencies are formed and rail operations rights are transferred to them, the information developed for rehabilitation projects can be used by the agencies to secure grants from $7.0 million appropriated for that purpose.

WSDOT continues to explore options for reconnecting the PV Hooper and P&L lines that was severed when a railroad trestle burned in August 2006 just east of Colfax.

Design Construction Impacts

Environmental Impacts / Compliance
No environmental compiance is required, because the railroad is already in operation.

Impacts to Traffic
Purchase of the railroad will provide an opportunity for shippers to continue to use rail as a modal choice in portions of eastern Washington.  Truck traffic should be reduced as a result.

Project Milestones Scheduled Attained Milestone Outlook
Phase 1 Purchase Complete Jun 2004 Nov 2004
Phase 2 Purchase Complete Aug 2005 May 2007
Begin Construction Jul 2008
Construction Complete Sep 2009 Funding after 2009 was removed from the "project."  Rehabilitation funds can be reappropriated under current legislative intention.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering
Right-of-Way
Construction $20.707 100%
Funded Project Costs $20.707 100%

Nickel funds included in above costs

$20.707 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Mike Rowswell, Freight Project Manager, 360-705-7930, Email RowsweM@wsdot.wa.gov, or Scott Witt, WSDOT Freight Strategy & Policy Office, 360-705-6903,  E-mail WittS@wsdot.wa.gov