Rail - Intermodal Infrastructure Enhancement Project - Port of Olympia

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
Intermodal Infrastructure Enhancements, Port of Olympia, Olympia, WA

Project Description
Expand rail infrastructure at the Port of Olympia's marine terminal by adding additional sidings, replacing ties, and installing active warning devices at the Market Street grade crossing.

Contractor/Consultant
Port of Olympia

Recent Progress
This project received three federal grants. The first two grants under Section 112 were combined into one. A grant agreement between the Federal Railroad Administration (FRA) and WSDOT was executed August 2007 to allow WSDOT to pass through the funds to the Port of Olympia. An agreement between WSDOT and the Port of Olympia was signed December 2007.

Scope of Work for the third grant under SAFETEA-LU was submitted to the FRA in November 2007.  Because the funds are based on a percentage of highway trust fund receipts received in a given federal fiscal year, the Port will not receive the full $0.684 million.  The Federal Highway Administration (FHWA) calculates this percentage each federal fiscal year and notifies WSDOT.

In March 2008 WSDOT received the go ahead from FRA  to complete the on-line grant application for the SAFETEA-LU grant and submit it for final processing.

Design Construction Impacts
No construction impacts are anticipated. 


Environmental Impacts / Compliance
Documentation for compliance with both National and State Environmental Policy Acts were completed. A biological assessment will be required for its affect on endangered species.

Impacts to Traffic
There will be minor traffic interference when grade crossing equipment is installed at the Market Street grade crossing.

Project Milestones Scheduled Attained Milestone Outlook
Engineering Begins Apr 2007 Sep 2006
Engineering Complete Jan 2008 Feb 2008
Environmental Documentation Complete Dec 2007 Feb 2008
Construction Begins Apr 2008 On schedule.
Construction Complete Jun 2009 On Schedule.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering
Right-of-Way
Construction
Funded Project Costs $2.664 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Carolyn Simmonds, Project Manager at 360.705.7992 or by Email at simmonc@wsdot.wa.gov