Rail - Port of Moses Lake/Northern Columbia Basin RR Engineering and Environmental

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
Northern Columbia Basin Railroad Project

Project Description
The first phase of this project will explore the feasibility and costs of several rail improvements intended to support economic development in the Moses Lake area.

Contractor/Consultant
The federal Surface Transportation Board (STB) Washington DC, HDR Engineering, Bellevue, WA

Recent Progress
The Surface Transportation Board (STB) agreed to allow WSDOT to be co-lead with the STB in performing the environmental study and documentation for the project.  HDR Engineering, Inc. will perform the work beginning in October 2006.  Development of the scope of work revealed a need to identify important plant community and habitat information in late spring and early summer due to the growing season of potential threatened, endangered, and candidate species.  As a result the draft environmental report cannot be completed until August 2007.  The final draft should be approved by May 2008.  WSDOT is working with its consultant to determine how much needs to be reappropriated for use in the next biennium.  The cost of the environmental work will leave about $650,000 of the total funding available for other work.  WSDOT is working with the Port of Moses Lake to explore appropriate use of the remaining funds.

Design Construction Impacts
The project does not include any construction at this time.  The next phase of the project will focus on the completion of environmental documents.

Environmental Impacts / Compliance
WSDOT, the Port of Moses Lake, and the federal STB will complete a thorough review of environmental impacts before any construction takes place.

Impacts to Traffic
The next phase of the project will have no impact on rail operations or roadway traffic.

Project Milestones Scheduled Attained Milestone Outlook
Project Definition Completed Nov 2006  Nov 2006 Project scope completed Aug 2005.  Study was completed Feb 2006. 
Preliminary Engineering Completed Feb 2007    
Environmental Documentation Completed May 2008   This assumes that only an Environmental Assessment is needed.  If the STB determines an EIS is needed, this milestone won't be met.
ROW Cert. Completed May 2008 Funding used in environmental documentation.  STB permitting delayed due to problems mentioned above for environmental documentation.
Project Evaluation Jun 2008
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $2.0 100%
Right-of-Way
Construction
Funded Project Costs $2.0 100%

Nickel funds included in above costs

$0

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Kevin Jeffers, Rail Engineering Manager at 360-705-7982 or E-mail: jefferk@wsdot.wa.gov