Recent Progress
The project was premised on the need to provide rail service to a livestock feed mill located on an industrial site developed by the Lincoln County Public Development Association (PDA). However, the tenant converted the operation to a biodiesel plant when the construction of the spur was delayed by uncertainties with the state's purchase of the CW Line of the Palouse River and Coulee City Railroad. Legal difficulties also occurred between the tenant and the PDA.
The need for the spur remains because the biodiesel plant can operate most efficiently if raw materials are shipped to it by rail. However, the remaining funds are not sufficient to construct the improvement.
|