Rail - Lewis and Clark RR - Vancouver Rail Improvements

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
Lewis and Clark RR/Vancouver - Rail Improvements, Vancouver, WA

Project Description
This $1.1 million project proactively upgrades the southern portion track on the Lewis & Clark (LC) short line in expectation of higher rail traffic over the next 15 years.

Contractor/Consultant
Lewis and Clark Railroad

Recent Progress
In the last 24 months, the rail has had increased carloads, because of a long term contracts with the Columbia Basin Railroad Company. Based on recent volume projection, it is anticipated there will be 10 percent annual growth for the next 15 years. Without this proactive work, the current track will erode resulting in poor service past 2013.

WSDOT awarded the Grant monies to Clark County in September 2007. Joint meetings between the County and WSDOT are scheduled for project Charter development and project planning.





Design Construction Impacts
This project will improve portions of the 14 miles of existing rail line on the southern portion of track on the Lewis & Clark short line to Battleground south. 



Environmental Impacts / Compliance
 This is a critical aspect of any WSDOT project. WSDOT makes every effort to assess and minimize environmental impact from our projects. During construction, WSDOT will reduce the impact to wetlands, creeks, and rivers in the project area.


Impacts to Traffic
Only minor impacts tolocal roadway traffic is anticipated during construction.

Project Milestones Scheduled Attained Milestone Outlook
Engineering Begins Jan 2008
Engineering Completed
Constructions Begins May 2008
Construction Completed Apr 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering
Right-of-Way
Construction
Funded Project Costs $1.1 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Lynnette Gregory, Project Manager at 360.705.7903 or by E-mail at gregorl@wsdot.wa.gov