Rail - King Street Station Renovation

Quarterly Project Report Update for Quarter Ending March 2008

Project Title & Location
King Street Station Renovation
Seattle, WA

Project Description
Renovates King Street Station

Contractor/Consultant
Otak, Design Work

Recent Progress
The donation agreement, essential to moving forward with construction, has been signed by BNSF and the city of Seattle.  King Street Station is now property of the city and the Seattle Department of Transportation (SDOT) is now the lead agency for this project.  WSDOT will transfer all federal funds to the city.  Funds in the King Street Station Account will also be made available to the city.  WSDOT is providing SDOT the drawings, scope description, and updated cost estimates to allow planned work to take place.  As a result, WSDOT will not be reporting future progress on this project.

SDOT expects to bid out the next piece of construction work in the next chapter.  This work will focus on the roof, including removal of unused microwave communication dishes, installing a new tile roof, replacing the roof drain system, cleaning and restoring the tower which will include repairing the clock and upgrading the electrical system.  The roof work is expected to begin in July and take four to five months to complete.  While the roof work is underway, SDOT will be working with consultants to finalize the design for the balance of the interior work.

SDOT is developing a construction strategy that will allow best use of federal grants, King Street Station Account money, and city funds.  In addition SDOT has $10.0 million to contribute towards the project.  This money will allow for a seismic retrofit of the building and reconstruction of the Jackson Street Plaza, both items not previously funded in the original WSDOT plan.  Transition of the project from WSDOT to SDOT will be completed in the second quarter of 2008. 

Design Construction Impacts

Environmental Impacts / Compliance
An EIS process was conducted in1995, updated in 1998 and in 2001.   A request for a documented categorical exclusion was submitted to FHWA in 2003.

Impacts to Traffic
Construction impacts will affect parking, taxi and general loading, and local vehicular traffic on Second and Third Avenues and King Street in downtown Seattle.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering Jul 2003 Jun 2004
Construction Begins Jul 2003 Jul 2003 Amtrak funded improvements completed.  Further work on hold pending agreements with SDOT.
Construction Complete Jun 2010 All responsibility for the remaining work has been transferred to the city of Seattle.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering
Right-of-Way
Construction $18.8 100%
Funded Project Costs $18.8 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Ron Sheck, Project Manager at 360.464.1202 or Email at sheckr@wsdot.wa.gov