Rail - King Street Station Track Improvements

Quarterly Project Report Update for Quarter Ending March 2006

Project Title & Location
King Street Station Track Improvements, Seattle, WA

Project Description
Renovates tracks, train platforms and other facilities to handle up to seven trains at one time.

Contractor/Consultant
BNSF Railway, Fort Worth, Texas

Recent Progress

WSDOT, BNSF Railway and Sound Transit have been working for some time on a preferred track design that works for all users of King Street Station.  However, Sound Transit needs the improvements completed to fulfill their contractual commitments to BNSF and begin operating nine daily round trips between Tacoma and Seattle, which they have scheduled for January 2008. 

 

To construct the “preferred” design, the unused I-90 on-ramp from 4th Ave needs to be removed and BNSF needs to purchase two properties.  WSDOT has only $3 million available in for this stage of the project, but the costs for this stage are anticipated to exceed $5 million.  The ramp removal is scheduled to go to construction in July 2006. The ramp removal and property purchases are scheduled to be complete by November 2006, if the funds are available.   Once the ramp removal and property acquisition is completed, the track construction is estimated to take about 20 months, which would mean Sound Transit could not expand their service until at least July 2008 without a change in their agreement with BNSF.

 

To avoid delaying their serve expansion, Sound Transit has directed BNSF to begin designing a modified track improvement that will fulfill their contractual commitments to BNSF and begin operating nine daily round trips between Tacoma and Seattle in January 2008.  However, this will make construction of the “preferred” plan more difficult and costly.  The precise cost and schedule ramifications of Sound Transit’s decision are not yet known.

Design Construction Impacts
Old I-90 off ramp will be removed to make way for new track in order for the main line to be relocated.

Environmental Impacts / Compliance
Environmental issues have not been identified at this time.

Impacts to Traffic
Temporary shoulder closures may occur on the I-90 off ramp to 4th Ave.  The project may impact freight and passenger operations when construction commences.

Project Milestones Scheduled Attained Milestone Outlook
Right-of-Way Complete Jul 2006 Late, but will be completed by June 2007.
Construction Begin Sep 2006 May be early on ramp removal.
Construction Complete Jun 2011
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.0 6%
Right-of-Way $2.0 13%
Construction $12.0 80%
Funded Project Costs $15.0 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

$15.0 100%

  For more information, go to www.wsdot.wa.gov/projects

Kevin Jeffers, Rail Engineering Manager at 360-705-7982 or E-mail:  jefferk@wsdot.wa.gov