Rail - Dayton Yard Rehabilitation - Port of Columbia County

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
Dayton Yard Rehabilitation – Port of Columbia County

Project Description
This project will upgrade tracks owned by the Port of Columbia.

Contractor/Consultant
Palouse River and Coulee City RR/Watco Companies

Recent Progress

The Seneca Green Giant asparagus cannery relocated away from Dayton several years ago and put its plant up for sale.  The Port of Columbia County located two prospective replacements to purchase the plant and begin operations.  However, rail upgrades were needed for the operations, so thelegislature provided $270,000 to assist with the needed infrastructure.  Subsequently the Green Giant property was removed from the market, and the prospective operators lost any incentive to locate in the area.  The Port identified an alternative project.  A private company was planning to allow use of a portion of its land as part of the project; however, the recent forest fires eliminated its ability to use land in another area, which created a need for it to use the land it had planned to donate.  As a result, the alternative project cannot be constructed.

The basis for the project no longer exists.  Although there is a general need to upgrade the yard tracks, the rail operator can continue to provide service for the foreseeable service at the current level.  WSDOT continues to explore alternative suggestions for use of the funds.

Design Construction Impacts

None have been identified at this time.

Environmental Impacts / Compliance
To be determined by the Port of Columbia County.

Impacts to Traffic
None have been identified at this time.

Project Milestones Scheduled Attained Milestone Outlook
Contract Complete Feb 2006 Pending
Construction Begins May 2006 Pending
Construction Complete Dec 2007 Pending
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering
Right-of-Way
Construction $0.270 100%
Funded Project Costs $0.270 100%

Nickel funds included in above costs

$0

2005 Transportation Partnership Account