Rail - Dayton Yard Rehabilitation - Port of Columbia County

Quarterly Project Report Update for Quarter Ending June 2006

Project Title & Location
Dayton Yard Rehabilitation – Port of Columbia County

Project Description
This project will upgrade tracks owned by the Port of Columbia.

Contractor/Consultant
Palouse River and Coulee City RR/Watco Companies

Recent Progress

Circumstances supporting the original project changed.  The Port identified an alternative project that must be evaluated by WSDOT to determine whether it falls within the scope of the original authorization.  It is uncertain at this time whether that is the case, and whether th ealternative project can be completed by June 30, 2007.

Design Construction Impacts

 

Environmental Impacts / Compliance
To be determined by the Port of Columbia County.

Impacts to Traffic

Project Milestones Scheduled Attained Milestone Outlook
Contract Complete Feb 2006 Pending
Construction Begins May 2006 Pending
Construction Complete Dec 2007 Pending
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering
Right-of-Way
Construction $0.270 100%
Funded Project Costs $0.270 100%

Nickel funds included in above costs

$0

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Susan Leverette Bagley, Asst. Rail Engineer @ 360-705-6902 or   E-mail: bagley@wsdot.wa.gov