Rail - White Swan/Toppenish - Yakama Sawmill Traffic Upgrades - Complete August 2008

Quarterly Project Report Update for Quarter Ending June 2008

Project Title & Location
Toppenish Simcoe and Western Yakama Sawmill Traffic Upgrades, Yakima County

Project Description
Upgrades existing Toppenish Simcoe & Western line for increased traffic from Yakama Tribe sawmill, supporting 225 jobs.

Contractor/Consultant
Yakima County, Columbia Basin Railroad

Recent Progress
WSDOT met with Yakima County in January 2008.  The county and WSDOT have decided to revert back to the original funding agreement in which the grant funds provide an upgrade to the Toppenish Simcoe and Western Rail Line between Wesley Junction (MP 0.00) and Town of Harrah (MP 9.6).  The work includes the purchase of materials and construction.

This project went to ad in May 2008; opening bids on May 21, 2008.  The winning bid was $70,000 over remaining grant funding.  The county will arrange for additional funds.  Construction is expected to start July 2008 with completion scheduled for April 2009. 

Design Construction Impacts
No construction impacts are anticipated.

Environmental Impacts / Compliance
No environmental impacts are anticipated.

Impacts to Traffic
Track work will be done around train operations.  Work in the vicinity of at-grade crossing could cause minor delays to vehicles in the area.

Project Milestones Scheduled Attained Milestone Outlook
Contract Complete Sep 2005 Sep 2005 Grant agreement signed. 
Construction Begins Jul 2008 May 2008 This project went to ad in May 2008; opening bids on May 21, 2008.
Construction Complete Jun 2009 Currently anticipated to be complete in April 2009.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering
Right-of-Way
Construction $0.64 100%
Funded Project Costs $0.64 100%

Nickel funds included in above costs

$0.64 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Lynnette Gregory, Project Manager at 360-705-7903, E-mail: gregorl@wsdot.wa.gov