Project Title & Location
Toppenish Simcoe and Western Yakama Sawmill Traffic Upgrades, Yakima County
|
Project Description
Upgrades existing Toppenish Simcoe & Western line for increased traffic from Yakama Tribe sawmill, supporting 225 jobs.
|
|
Contractor/Consultant
Yakima County, Columbia Basin Railroad
|
|
Recent Progress
WSDOT met with Yakima County in January 2008. The county and WSDOT have decided to revert back to the original funding agreement in which the grant funds provide an upgrade to the Toppenish Simcoe and Western Rail Line between Wesley Junction (MP 0.00) and Town of Harrah (MP 9.6). The work includes the purchase of materials and construction.
This project went to ad in May 2008; opening bids on May 21, 2008. The winning bid was $70,000 over remaining grant funding. The county will arrange for additional funds. Construction is expected to start July 2008 with completion scheduled for April 2009.
|
|
Design Construction Impacts
No construction impacts are anticipated.
|
|
Environmental Impacts / Compliance
No environmental impacts are anticipated.
|
Impacts to Traffic
Track work will be done around train operations. Work in the vicinity of at-grade crossing could cause minor delays to vehicles in the area.
|