ENVIRONMENTAL PERMITTING

back to flowchart

CLEAN WATER ACT SECTION 404/10
Requirement Description Authority
CFR, RCW, WAC
Additional Information MDL No.
Public Comment The USACE will obtain comments from agencies and the public on the permit application. 23 CFR 772.11 Must be completed in no more than 30 days after notice of public availability issued.  
Public Hearing A public hearing is not common but the public may request that the USACE conduct a hearing.      

back to Project Delivery Process

download Excel spreadsheet