ENVIRONMENTAL PERMITTING

Flowchart depicting the Coast Guard Bridge Permit process.  Click the chart to get more information.

flowchart legend

back to Project Delivery Process
 

top
 


  Copyright WSDOT © 2005

    Traffic & Roads | Search | Contact WSDOT | WSDOT Business | WSDOT Home

Coast Guard Bridge Permit Submit Completed JARPA 30-Day Public Comment Period Receive 401 Water Quality Certification Receive Coastal Zone Management Certification Receive Biological Opinion (if applicable) Complete Necessary NEPA Documentation Permit Decision Possible Appeal to Commandant of U.S. Coast Guard Permit Issued