Washington State Department of Transportation
WSDOT NewsSearchContact WSDOTWSDOT Home
Traffic & RoadsProjectsBusinessEnvironmentalMaps & Data
Accountability
 
  Project Management
  Project Management Process
  Project Delivery Information System
  Master Deliverables List
  Project Management Training
  Project Legal Requirements
 
 


Project Legal Requirements

ENVIRONMENTAL PERMITTING

Flowchart depicting the National Pollution Discharge Elimination System (NPDES) process.  Click the chart to get more information.

flowchart legend

National Pollutional Discharge Elimination System (NPDES) and State Waste Discharge NPDES Construction Stormwater Permit (General and Individual) NPDES Industrial Stormwater Permit (General) Develop Stormwater Pollution Prevention Plan (SWPPP) Determination of Stormwater Exposure Submit Notice of Intent Prepare/Submit NPDES Individual or Alternative General Permit Application Submit General Permit Application and SWPPP Complete No Exposure Application On-Line Submit Notice of Intent 30-Day Comment Period, May request Hearing Application Reviewed/Decision Made Permit Issued Permit Denied Denial Appeal Possible to Washington Pollution Control Hearing Board No Permit Coverage Required Other NPDES Permits NPDES Sand and Gravel Permit (General and Individual) NPDES Municipal Stormwater Permit (General) NPDES Industrial Stormwater Permit (Individual) State Waste Discharge Permit

back to Project Delivery Process
 

top
 


  Copyright WSDOT © 2005

    Traffic & Roads | Search | Contact WSDOT | WSDOT Business | WSDOT Home