HYDRAULIC PROJECT APPROVAL
Requirement Description Authority
CFR, RCW, WAC
Additional Information MDL No.
Hydraulic Project Approval Hydraulic Project Approval (HPA) A permit required for projects that use, divert, obstruct, or change the natural flow or bed of any state waters (e.g. culvert work, realignment, bridge replacement). JARPA can be used. RCW 77.55.100; WAC 220-110-030   PE-D-31.04