| Contract Adjustment
|
If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly.
|
23 CFR 635.109(2)(ii)
|
Upon Receipt of Request for Adjustment
|
|