| Request for Adjustment
|
If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment.
|
23 CFR 635.109(2)
|
Within 7 calendar days of receipt of the notice to resume work.
|
|