| Engineer Investigation
|
An engineer will investigate the conditions, and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding anticipated profits, will be made and the contract modified in writing accordingly.
|
23 CFR 635.109(1)(ii)
|
Upon Notification of Differing Site Conditions
|
|