| CONTRACTING
|
| Requirement |
Description |
Authority
CFR, RCW, WAC |
Additional Information |
MDL No. |
| Notification of Differing Site Conditions
|
During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions.
|
23 CFR 635.109(1)
|
Notification before the site is disturbed and before the affected work is performed.
|
|