Pre-Construction

Online Guide

Plan the Work

Process

Activity:

Validate Project Budget

Revision

July 1, 2005

Description:

Validate Programmed Project Budget from the Capital Project Management System (CPMS) through comparison with specific Project Planning.

Inputs:

·        Completed Initiate and Align Worksheet

·        Completed Work Breakdown Structure (WBS)

·        Performance Baseline Schedule for Endorsement

Tools:

·        WSDOT Project Delivery Information System (PDIS)

·Note: This is a WSDOT internal web site that is not available to anyone outside the agency

·        WSDOT Urban Corridors Office scheduling

·Note: This is a WSDOT internal web site that is not available to anyone outside the agency

·        WSDOT Ferries scheduling

Note: This is a WSDOT internal web site that is not available to anyone outside the agency

·        Capital Program Management System

Steps:

1.      Compare the Estimated Project Costs from the Resource-loaded Schedule to the programmed Project Budget provided in the CPMS.

2.      Identify any variances between project-estimated costs and programmed budget, including their sources (scope elements, resource costs, etc.).

3.      Review and reconcile all budget differences with Region/Organization Management.

4.      Based on reconciled project budgets and the Performance Baseline Schedule, develop the Project Aging Report.

Products:

·        Updated Project Budget

·        Project Aging Report

Guidelines:

The development of Project Costs and the Project Aging Report requires familiarity with PDIS and is best approached through consultation with Region/Organization Program Management staff.