Pre-Construction |
||
|
Plan the Work |
|||
|
Activity: |
Validate Project
Budget |
Revision July 1, 2005 |
|
|
Description: |
Validate Programmed Project Budget from the Capital Project Management System (CPMS) through comparison with specific Project Planning. |
||
|
Inputs: |
·
Completed
Initiate and Align Worksheet ·
Completed
Work Breakdown Structure (WBS) · Performance Baseline Schedule for Endorsement |
||
|
Tools: |
·
WSDOT Project Delivery
Information System (PDIS)
·
WSDOT Urban
Corridors Office scheduling
Note: This is a WSDOT internal web site that is not available to
anyone outside the agency · Capital Program Management System |
||
|
Steps: |
1. Compare the Estimated Project Costs from the Resource-loaded Schedule to the programmed Project Budget provided in the CPMS. |
||
|
2. Identify any variances between project-estimated costs and programmed budget, including their sources (scope elements, resource costs, etc.). |
|||
|
3. Review and reconcile all budget differences with Region/Organization Management. |
|||
|
4.
Based on reconciled project
budgets and the Performance
Baseline Schedule, develop the Project Aging Report. |
|||
|
Products: |
·
Updated Project Budget ·
Project Aging Report |
||
|
Guidelines: |
The development of Project Costs and the Project Aging Report requires familiarity with PDIS and is best approached through consultation with Region/Organization Program Management staff. |
||