|
|
Construction |
||
|
Plan the Work |
|||
|
Activity: |
Task Planning and
Scheduling |
Revision July 1, 2005 |
|
|
Description: |
Using the Work Breakdown Structure to develop “manageable” tasks, allocating resources needed for performance and putting them into a time-phased format—Scheduling. |
||
|
Inputs: |
·
Construction
Phase Work Breakdown Structure (WBS) ·
Contractor
Construction Schedule (if available; otherwise, the Working Day Schedule) ·
Contract
Documents · Record of Materials |
||
|
Tools: |
·
WSDOT Project
Delivery Information System (PDIS) Note: This is a WSDOT internal web site that is not available to anyone outside the agency · WSDOT Construction Manual |
||
|
Steps: |
1. Define Tasks/Activity definition (Levels 5-10) The Task Planning Worksheet is an excellent tool to help with identifying and defining detailed Tasks that support the production of the deliverables (Level 4). The Task Planning Worksheet helps organize task information, including task description, resources needed, predecessors, successors, etc. |
||
|
2. Establish Durations and Task Dependencies: Review the approved Contractor Construction Schedule if it is available or the Working Day Schedule and develop duration estimates and/or Start/Finish dates for all tasks. Note that the Working Day Schedule is used prior to receiving the Contractor Construction Schedule. If the Working Day Schedule was used to develop the Plan, then it should be updated once the Contractor Construction Schedule is approved. The Plan should be further updated after major delays, winter shutdowns, or changes that affect the total time for completion. Review
the schedule, dates, and Major Milestones for appropriateness. |
|||
|
3. Review each task and assign resources and/or estimated costs to the tasks– (generic resources are a minimum): ·
Identify the
estimated effort needed for the assigned resource. Determine whether the resource will be uniformly
assigned at a set rate (e.g., 8 hours/day) or a total
planned effort in total work units (e.g.,
40hours total effort). ·
Identify any
constraints associated with the assigned resource (i.e., resource is only
available after Oct 15th, or resource is only available 50% of the time) Be sure to include Dollar-loaded deliverables prepared by specialty groups. |
|||
|
4. Balance resources for the project and across multiple projects. Based on appropriate criteria (e.g., resource availability, funding, completion of Major Milestones), shift task performance periods, revise priorities, identify additional resources, or modify approaches to performance, etc., to establish a balanced plan for the use of resources. |
|||
|
5. Review the “balanced” Construction Engineering Workforce Plan with team members prior to seeking endorsement. |
|||
|
Products: |
·
Construction
Engineering Workforce Plan for Endorsement |
||
|
Guidelines: |
N/A |
||