Recent Progress
Construction is physically complete on the first phase of this project, 6th Avenue to Jackson Avenue.
The second phase, 36th Street to Olympic Drive, has been accelerated seven months; bids for the work were opened in December 2004. Construction began in early May. The contractor completed the median widening and precast barrier installation. The westbound pavement has been overlaid. The eastbound onramp at Olympic is being widened and a new noise wall is being installed. Due to bad weather the final eastbound overlay has been delayed to late Spring 2006.
The final phase of the project, Union to Jackson Avenue, was awarded Feb. 7, 2005. Construction activities began March 11. All the drilled shafts for the bridges have been completed. The columns at the Snake Lake structures have been poured and the falsework is being installed for the eastbound bridge widening. Piers 2 and 3 are nearly complete for the Center Street bridge and the steel girder components are arriving at the job site. The abutments have been built and the prestressed girders placed at the 12th Street bridge. The Piers at the 6th Ave bridge are complete and falsework is being installed for the CIP box girder. The piers at the Pearl Street Bridge are nearly complete.
Approximately 400,000 cubic yards of earth have been excavated, of which 100,000 cubic yards has been placed in embankment areas on the project.
The base lift of HMA was placed for the new alignment between Snake Lake and 19th Street.
New stormwater ponds have been constructed at Union Ave, Mullen Street, near Lowes, next to the JJ wetland , at 12th Street and at Pearl Street.
Two soil nail retaining walls have been constructed under the 19th Street bridge, three MSE walls have been constructed for the Center St. ramps, one cantilever wall was constructed at the JJ pond and another at the new frontage road. A noise wall is under construction near Snake Lake and another at the 6th Ave offramp.
|