Recent Progress
Construction is physically complete on the first phase of this project, 6th Avenue to Jackson Avenue. Construction is physically complete on the second phase of this project, 36th Street to Olympic Drive. Construction is substantially complete on the third phase of this project, Union Avenue to Jackson Avenue.
Accomplishments Substantial completion was granted for the Union Ave to Jackson Ave phase on March 6, 2007.
The new Center Street offramp opened December 21, 2006. Eastbound HOV lane opened to traffic January 26, 2007. The new frontage road between 6th Ave and Pearl St. opened February 8, 2007.
Upcoming Activities Ribbon Cutting Ceremony for Scott Pierson Trail scheduled for May 12, 2007 at Cheney Stadium.
Ramp metering systems may be put into service in the westbound direction XXX. Ramp metering in the eastbound direction will be activated to coincide with the opening of the new Tacoma Narrows Bridge. Other ITS elements like traffic flow information on the internet will be available by XXX .
Plant Establishment at Snake Lake will continue until early 2008.
|