SR 16 - Westbound Nalley Valley

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
SR 16 / I-5 - Westbound Nalley Valley, Tacoma.

Project Description
This project is the first of three projects to rebuild the I-5/SR 16 Nalley Valley interchange in Tacoma. The existing bridges are too narrow to carry additional lanes and the unique structure-type prevents widening. This project improves safety and increases mobility by eliminating traffic weave, adding new lanes and building dedicated ramps to Sprague Avenue. Work includes building a new westbound viaduct, new ramps between SR 16 and Sprague Avenue and new ramps from I-5 to WB SR 16.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

Design: The project team will submit a 60% design review mid-September. 

 

Construction: The project is on track for construction bidding in March 2008.

Design Construction Impacts

Environmental Impacts / Compliance

NEPA re-evaluation - Assessing potential mitigations sites for 0.1 AC of wetland impact; Nalley Valley Viaduct has been identified as a possible candidate for the Register of Historic Bridges, may need to do a supplement to the Environmental Assessment; Air and Noise analysis is being re-analyzed for 2030 traffic numbers.  

Impacts to Traffic
Long-term closure of Sprague Avenue, short-term closures of southbound  I-5 to 38th Street off-ramp and 38th Street to westbound SR  16 on-ramp. There will also be night-time closures on I-5, Center Street and South Tacoma Way for girder placement and other construction work.

Project Milestones Scheduled Attained Milestone Outlook
Design Documentation Complete January 2007 DN Approval Achieved October 2000.
Contract Ad March 2008
Groundbreaking June 2008
Open to Traffic July 2010
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 11.0 6.8%
Right-of-Way 11.3 6.9%
Construction 140.3 86.3%
Funded Project Costs 162.6 100%

Nickel funds included in above costs

142.2 87.5%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects